Springfield Water System tentative schedule

S.U.R. Construction West, Inc.

Springfield, VT – Water System Improvements Contract I2

Two Week Look Ahead Schedule

 

July 20 – 24, 2026

o   Layout and sawcut the water line trench

o   Set up staging area

 

July 27 – 31, 2026 (South St. & Main St.)

o   Perform a couple designated test pits and get an idea on soil in those areas at same time.

o   Make sure our plan and system for contaminated soils with the crew and Pathways are understood and in place

o   Distribute Water Shutdown notices as reviewed with the Town Water Dept.

o   Install all temp inlet protection

o   Connect to Existing 10” water main on South St at STA 0+00

o   Install water main on South St toward Grove St (roughly 100 feet per day)

 

August 3 – 7, 2026 (South Street)

o   South St water main installation; Connect to existing main on Grove Street

o   Water main install to STA 2+00 on Main St to connect to existing