Springfield Water System tentative schedule
S.U.R. Construction West, Inc.
Springfield, VT – Water System Improvements Contract I2
Two Week Look Ahead Schedule
July 20 – 24, 2026
o Layout and sawcut the water line trench
o Set up staging area
July 27 – 31, 2026 (South St. & Main St.)
o Perform a couple designated test pits and get an idea on soil in those areas at same time.
o Make sure our plan and system for contaminated soils with the crew and Pathways are understood and in place
o Distribute Water Shutdown notices as reviewed with the Town Water Dept.
o Install all temp inlet protection
o Connect to Existing 10” water main on South St at STA 0+00
o Install water main on South St toward Grove St (roughly 100 feet per day)
August 3 – 7, 2026 (South Street)
o South St water main installation; Connect to existing main on Grove Street
o Water main install to STA 2+00 on Main St to connect to existing